ADU Permits in California: The 2024 Guide to Fast Approval

Are you considering adding an Accessory Dwelling Unit (ADU) to your property? Whether you want to expand your living space, generate rental income, or house a family member, going through the permitting process doesn't have to be intimidating.

Multitaskr 100 ADU financing promo banner

Mastering ADU Permits, Your Key to Smooth Approval

writer-fernanda-castillo-multitaskr

Fernanda Castillo

Learn all about the approval process for your permits and how to avoid costly mistakes, ensuring a hassle-free journey to achieving your ADU goals.

1

What Is An ADU Permit?

2

Most Required ADU Permits

3

How to Apply for an ADU Permit?

Book a Free Consultation to see how you could benefit!

What Is An ADU Permit? 

An ADU permit is an official document from local authorities that allows homeowners to build or modify an ADU on their property. This permit grants legal approval for renovating, constructing, or converting a structure or unused space into an ADU, ensuring compliance with building codes, zoning regulations, and other local ordinances. 

 

Do You Need A Permit To Build An Adu?

Yes, obtaining a permit is required to build an ADU in California. 

The process may vary depending on your location and the specific regulations of your city. However, a permit is required before starting any construction or renovation work. It’s important to keep in mind that failing to obtain the necessary permits can result in fines, legal complications, and even the demolition of unauthorized structures, so always make sure to consult with your local building department or permitting authority to understand the appropriate requirements for your ADU project.


Standard ADU Ordinances

California’s ADU permitting process involves navigating a complex web of regulations. From planning considerations to zoning restrictions and parking requirements, these standard ordinances significantly impact the feasibility and design of your ADU project. 

Planning

Required rooms & amenities

ADU regulations often outline the minimum requirements for the design, including the number of rooms and essential amenities. These may include specifications for bedrooms, bathrooms, kitchens, and living spaces, ensuring that ADUs provide adequate accommodation for occupants while maintaining functionality and comfort.

An ADU must have a bedroom, a kitchen or kitchenette, a bathroom, a living space, a storage room, and accessibility features as needed, depending on local building codes and available space.

Zoning

City & county restrictions

In addition to the state’s regulations on ADUs, cities and counties may also have their own restrictions. These restrictions may pertain to the size of the unit, the number of occupants allowed, the duration for which it can be rented out, and even the permitted architectural style. 

ADU parking requirements & restrictions

Parking requirements are a very common element of ADU regulations, with many jurisdictions requiring enough spaces for the unit tenants. These requirements aim to relieve congestion in residential areas and ensure adequate availability for both the primary residences and ADUs. 

An ADU is exempted from requiring a parking spot under certain circumstances:

  • It is within a one-half-mile radius of public transportation or one block of a car-share location.
  • It is located in an architecturally and historically significant district.
  • It is part of the existing primary residence or an accessory structure.
  • It is situated within one block of a car-share vehicle.
  • It is in an area where on-street parking permits are mandated but have yet to be made available to the ADU’s occupants.

Also, remember that if these spaces are removed to construct an ADU or transformed into one, they do not need to be replaced.

Ready to navigate the ADU process with ease? Explore our dedicated pages for San Diego County ADU Regulations and Los Angeles County ADU Regulations to ensure compliance and streamline your ADU project today.

 

Most Required ADU Permits

Building Permit

The building permit is one of the main requirements to construct an ADU. It is vital to ensure that the unit complies with local building codes, zoning laws, and safety regulations, including fire safety, accessibility, and general building standards. 

Electrical and Plumbing Permit

This type of permit is also essential for ADU projects, as it covers installing, modifying, or repairing electrical and plumbing systems within the unit. They ensure all work is done safely and complies with building codes and standards. 

Local Permits

In addition to building, electrical, and plumbing permits, your project may require other permits depending on your local jurisdiction. These permits could include planning, zoning, grading, or environmental approvals to ensure compliance with city or county regulations.

 

How to Apply for an ADU Permit?

Securing a permit for your ADU involves a multi-step process that varies depending on your local jurisdiction. Here’s a general overview of the steps involved:

Step 1: Plan Submission & City Initial Review Process

Begin by submitting your ADU plans to your city or county planning department. These plans should include detailed drawings, floor plans, site plans, and any other required documentation. The city will then conduct an initial review to ensure your plans comply with local zoning regulations, building codes, and other applicable requirements.

Step 2: Response & Resubmission

After the initial review, you may receive feedback or requests for revisions from the city or county. Address any issues and make the necessary adjustments to your plans. Then, once revised, resubmit your updated plans for further review.

Step 3: Plan Checker Reviews Resubmission

Upon resubmission, your revised plans will undergo another round of review by plan checkers. These professionals will thoroughly examine your plans to verify compliance with building codes, structural requirements, fire safety standards, and other relevant regulations. Be prepared to address any additional feedback or modifications requested during this stage.

Step 4: City Final Review Process

Once the plan checkers approve your revised plans, they will go through a final review by the city or county planning department. This review ensures that all necessary permits have been obtained and that the proposed ADU project aligns with all applicable regulations and ordinances. If everything meets the requirements, you’ll receive the final approval to proceed with construction.

How Much Do ADU Permits Cost?

What Fees Do I Have to Pay When Building My ADU?

When planning your ADU project, it’s crucial to budget for the various fees imposed by your local jurisdiction. Here are some common fees you may encounter:

Plan Check Fee

Before your ADU plans are approved, they undergo a thorough review by city or county officials to ensure compliance with building codes and regulations. This review incurs a plan check fee, which covers the cost of evaluating your plans for structural integrity, safety, and adherence to zoning ordinances. Depending on the size of the construction area, it usually oscillates between $1,700 and $2,000+. 

For example, the plan check fee in San Diego County is $1,711 + $0.362/sf. To calculate the total fee, add the fixed fee ($1,711) to the fee per square foot multiplied by the total square footage of the construction area.

So, if we say that the construction area is 1,000 square feet, the calculation would be:

Plan Check Fee = $1,711 + ($0.362/sf * 1,000 sf) = $1,711 + $362 = $2,073

Your total fee would be $2,073.

Building Permit Fee

Once your plans pass the review process, you must obtain a building permit to start construction on your ADU. The building permit fee varies depending on the size and scope of your project and local regulations. This fee contributes to the administrative costs associated with issuing permits and conducting inspections throughout construction. Depending on your zone, a building permit fee usually ranges from $1,400 to $2,000+. 

Following the example from above, the building permit fee in San Diego County is $1,444 + $0.486/sf. If we say that the construction area is 1,000 square feet, the calculation would be:

Building Permit Fee = $1,444 + ($0.486/sf * 1,000 sf) = $1,444 + $486 = $1,930

Your total building permit fee would be $1,930.

Impact Fee

Impact fees vary depending on your locality and the amount set by local authorities, similar to school and fire mitigation fees. In some jurisdictions, ADU projects may be subject to impact fees designed to mitigate the strain on public infrastructure and services caused by new development. These fees vary widely depending on factors such as location, project size, and local policies. Impact fees typically contribute to funding public amenities, transportation improvements, and utilities necessary to support community growth.

Understanding the breakdown of these fees is essential for accurately estimating the total cost of your ADU project. Consult with your local planning department or building authority to obtain precise information on fee structures and payment requirements specific to your area. By budgeting effectively and accounting for all associated costs, you can better manage the permitting process and successfully realize your ADU vision.

 

How Long Does It Take To Get An ADU Permit?

Getting the necessary permits for your ADU is crucial in adding an ADU to your property. However, the timeline for obtaining these permits can vary depending on your location and local regulations. Let’s explore the typical ADU permitting timelines in two major counties in California.

San Diego County ADU Permitting Timeline 

An approximation for the San Diego County ADU permitting timeline depends on factors such as the complexity of the project, local regulations, and the workload of the permitting department. However, the ADU permitting process in San Diego County may take anywhere from 2 to 4 months from the submission of the application to final approval.

Los Angeles County ADU Permitting Timeline

A rough estimate for the Los Angeles County ADU permitting timeline can vary widely based on several factors, including the project’s complexity, the permitting department’s workload, and any specific requirements or regulations applicable to the property or location. However, a general estimate for the ADU permitting process in Los Angeles County could range from approximately 3 to 6 months from application submission to final approval. This timeline includes the review of ADU plans, the issuance of permits, construction, and final inspection and approval stages. Keep in mind that unexpected delays or additional requirements may extend this timeline further. It’s advisable to consult with local authorities or permitting agencies for more accurate estimates based on your specific project details.

 

Costly ADU Permitting Mistakes To Avoid

Planning for an ADU can be exciting, but understanding potential challenges is essential to prevent expensive errors. This section will examine typical red and yellow flags that may affect your ADU project and effective strategies to overcome them.

  1. Fire Hazard Zones

One of the most critical considerations when planning an ADU is the property’s location in a high fire hazard severity zone. These zones can pose significant challenges to ADU projects due to stringent regulations aimed at fire safety. Before embarking on your project, it’s essential to determine if your property falls within such a zone. 

  1. Specific Plan Areas

Properties located within specific plan areas may be subject to additional rules and regulations that could impact ADU construction. These areas often have unique zoning requirements or restrictions that homeowners must adhere to when planning their ADUs.

  1. Environmental Restrictions

Environmental factors such as coastal zones, creeks, or other protected areas can significantly impact ADU construction. These regulations may restrict building activities or require additional permits, leading to unexpected delays and expenses. 

  1. Setback Requirements

Understanding setback requirements is crucial for determining the allowable building footprint for your ADU. Setback regulations dictate how far structures must be positioned from property lines, roads, or other structures. You can avoid costly revisions or project delays by complying with setback requirements.

  1. Front Yard Setbacks and Corner Lots

Front yard setbacks, especially on corner lots, can pose challenges for ADU construction. While regulations may allow for reduced setbacks in rear and side yards, front yard setbacks are often subject to stricter requirements. 

  1. Access and Emergency Services

Accessibility to emergency services, such as fire departments, is crucial for ADU projects. Properties located far from roads or needing adequate access for emergency vehicles may face additional requirements or restrictions. Working closely with local authorities and fire departments can help ensure that your ADU project meets all accessibility and safety standards.

 

Before starting your ADU project, it’s crucial to consult with your local authorities to obtain valuable guidance. Conducting thorough research, seeking professional advice, and complying with all local regulations and ordinances are essential to ensure a successful ADU construction experience. Remember to prioritize these steps to avoid potential issues and set up your project for success.

Conclusion

Obtaining permits for your ADUs in California doesn’t have to be a challenging task. With the insights provided in this comprehensive guide, you can confidently embark on your ADU journey, knowing the key steps and considerations to ensure a smooth approval process.

However, if you’re seeking expert assistance to streamline the entire ADU journey and effortlessly navigate the permitting process, look no further than Multitaskr. Our team of professionals specializes in ADU project management, handling everything from permit applications to construction oversight with precision and expertise.

Take the first step towards realizing your ADU project goals by booking a free consultation with Multitaskr today. Whether you’re planning to expand your living space, generate rental income, or accommodate multi-generational living, we’re here to help you every step of the way – schedule your consultation and start your project today!

Share This Story!

Share On Facebook
Share On Twitter
Share On Linkedin
Share On Pinterest
Share On Email

Book a Free Consultation to see how you could benefit!

Multitaskr blogs

This might interest you

Is Your ADU Dream Feasible with SB9?

Is Your ADU Dream Feasible with SB9?

Many homeowners face problems before construction even begins because they do not have the right information to take on the feasibility of a home-improvement project.
The White House, ADU and the future of affordable housing

The White House: ADUs and The Future of Affordable Housing

The government agrees that building ADUs are the best option to provide affordable housing and maximize the income of every homeowner.
Multitaskr - Blog Freddie Mac SD

Freddie Mac Eases ADU Financing for Affordable Living

Get fully financed to build more Accessory Dwelling Units (ADUs), generate rental income, and increase your property value with Freddie Mac’s new policy update!

100% ADU

FINANCING

AVAILABLE

DEFERRED PAYMENTS FOR UP TO 18 MONTHS

Your ADU made simple!

X